Grand RE Scam Revealed: What Subsidised Wind & Solar Power Is Really Costing You

Wind and solar scammers don’t want you to know what’s causing your rocketing power bills, and those profiting from endless wind and solar subsidies want to keep it that way.

There are a raft of direct and indirect subsidies to wind and solar, which the vaguely interested are able to soon identify. However, it’s the systemwide costs of attempting to rely on sunshine and breezes that really add up.

Placing diffuse and intermittent energy generation sources – like hundreds of industrial wind turbines and thousands of solar panels – in remote locations may have local land use and environmental consequences, but for the power consumer it’s the cost of bringing that (occasionally) generated power to market that’s the real kicker.

In Australia, the cost of bringing occasional power from remote locations is adding hundreds of millions of dollars to power consumers’ bills, every year.

Predictably, whenever wind and solar outfits are faced with liability for the cost of building the networks required to deliver their sporadic offerings to market, they cry foul.

In the US, wind and solar rent-seekers are up in arms because hopeful new entrants to the grand wind and solar scam might just be forced to pay the costs of extending networks to their remote solar and wind plants out of their own pockets. Which means many of these threatened projects will never be built.

The Hill: Forcing Renewable Operators to Pay for Network Upgrades is Impeding the Green Energy Revolution
Watts Up With That?
Eric Worrall
21 August 2021

According to The Hill and industry advocates, it’s deeply unfair that the government is unfairly trying to force renewable energy providers to pay the full cost of power line upgrades required to bring cheaper electricity to American homes. The government is also cruelly forcing green entrepreneurs to submit to lengthy planning processes.

Regulatory overhaul is key to the clean energy transition
The Hill
Devin Hartman
20 August 2021

As Congress contemplates clean energy subsidies and standards, we should first ask why clean energy deployment can’t already keep up with burgeoning demand. The answer is simple to identify but difficult to remedy: archaic regulation. Regulatory solutions aren’t as sexy as grandiose public spending, but for those motivated by results over optics, it’s time to redefine clean energy leadership.

The infrastructure deal relies on a controversial budgetary approach to clean energy, but America needs unified regulatory reform. The deal, as it currently stands, includes a one-time injection of $73 billion for clean energy and electric transmission. To put this in perspective, utilities spent over a quarter trillion on transmission alone over the past decade. The problem isn’t the private sector’s unwillingness to spend, but a regulatory structure that deters private investment and insulates incumbent utilities from competition. For example, Congress should be asking why transmission regulation is a “protection racket” that rewards utilities for spending excessively while deterring innovative, low-cost alternatives that would save consumers billions and accelerate decarbonization.

For starters, a slew of regulatory flaws in electricity market rules and governance insulate incumbent power plants from clean, competitive new entrants. A report by Americans for a Clean Energy Grid outlines the imperative of overhauling grid regulation, noting that the current system is “causing a massive backlog and delay in the construction of new power projects.” New projects backlogged in the grid interconnection process already equal 77 percent of the total capacity of all existing power plants.

Today’s regulatory state is the antithesis of the Wall Street refrain on sustainable finance: “speed to market.” Forcing taxpayers and consumers to pay for what the private sector wants to finance but can’t build is impractical and unjust. Aside from research and development assistance, clean energy leadership must divorce itself from spending others’ money. Congressional efforts should instead prioritize unleashing the might of the strongest economic force in history: American free enterprise.
The Hill

If you read The Hill article and were left with a weird disjointed feeling that the author never actually explained their problem, you are not alone. But delving into one of the referenced reports, by Americans for a Clean Energy Grid, we finally see them spell out their grief.

Disconnected – The Need for a New Generator Interconnection Policy
Americans for a Clean Energy Grid
Clay Caspary, Michael Goggin, Rob Gramlich and Jesse Schneider
January 2021

I. Executive Summary

… (page 5)

Although FERC and the RTOs have undertaken worthwhile reforms to alleviate interconnection backlogs, the interconnection queues are costly, lengthy, and unpredictable. Power project developers are uncertain if their project will be approved and this risk significantly increases the cost of capital for generation developers, which increases the cost of energy for customers.

The current process also places nearly all costs of network upgrades on the energy project developer, even though many others will benefit from the construction of the project. Until a few years ago, these interconnection charges for new renewable resources would comprise under 10 percent of the total project cost for most projects. In recent years – due to the lack of sufficient large-scale transmission build – these costs have dramatically risen and interconnection charges now can comprise as much as 50 to 100 percent of the generation project costs. The system has reached a breaking point recently as spare transmission has been used up. Presently in most regions, new network capacity is needed for almost all of the projects in the queues.

Participant funding for new grid connections is no longer a “just and reasonable” policy and violates FERC’s “beneficiary pays” principle and the Federal Power Act. Relying on the interconnection process to identify needed transmission leads to a piecemeal approach and inefficiently small upgrades, raising costs to consumers. The incremental reforms at the RTO-level over the past decade have only served to treat symptoms of this fundamental issue – the lack of alignment between regional planning processes and the interconnection process.

… (page 20)

The failure of the current system under the new resource mix, including excessive costs and risk, an inability to build needed transmission, and generators paying for large network upgrades that primarily benefit customers suggest that participant funding may no longer be a just and reasonable policy. Participant funding of network upgrades not only imposes costs on interconnection customers that are often exorbitant and rising, but is also not the solution to the inability to build large-scale transmission.

One policy solution would be to end participant funding for new generation. It is clear that major network upgrades resulting from generation interconnection requests provide economic and reliability benefits to loads and reduce congestion to improve grid efficiencies and operational flexibility, and therefore should not be direct assigned as a result of participant funding. The Commission can and should change this policy within the scope of interconnection policy.
Americans for a Clean Energy Grid

Renewable energy entrepreneurs don’t want to pay the full cost of power transmission network upgrades required to bring their product to market, they want to force coal, gas and nuclear plant operators to share some of the cost burden.

Renewable entrepreneurs argue that the network upgrades they are demanding would improve the overall electricity network resilience. There may be a grain of truth in this, but I suggest the vast bulk of the network upgrades renewables entrepreneurs are demanding, like running high capacity transmission networks into the middle of whatever remote wasteland or mountain top hosts their new wind and solar arrays, would likely only be economically useful to the renewable entrepreneurs themselves.

If renewable operators get their way, by forcing every provider to help pay for the upgrades they alone want, in my opinion this would trap ordinary people into paying more for electricity. If renewable energy entrepreneurs alone have to pay the full economic cost of their product, they still have to compete against the existing prices of coal, gas and nuclear electricity plant operators. But if everyone has to pay a share, there is no escape for ordinary people from higher costs. Every provider would have to jack up their electricity prices to end users, to pay for their share of the cost of electricity network upgrades most of them do not want and do not need.
Watts Up With That?

6 thoughts on “Grand RE Scam Revealed: What Subsidised Wind & Solar Power Is Really Costing You

  1. Who in their right mind wants to rely on breezes and sunshine for a continuous uninterruptible supply of electricity? Intermittent electricity from breezes and sunshine, has not, and will not, run the economies of the world, as electricity alone is unable to support the prolific growth rates of the medical industry, military, airlines, cruise ships, supertankers, container shipping, and trucking infrastructures to meet the demands of the exploding world population.

    Only healthy and wealthy countries like the USA, Germany, Australia, and the UK can subsidize electricity from breezes and sunshine, and intermittent electricity at best. The 80 percent of the 8 billion on earth living on less than 10 dollars a day cannot subsidize themselves out of a paper bag. Those poorer countries must rely on affordable and abundant coal for reliable electricity, while residents in the healthy and wealthier countries pay dearly for those subsidies with some of the highest cost for electricity in the world.

  2. Does the sun operate according to the requirements of photovoltaic experts?
    The design uses 12 500W modules, a total of 6kW modules, and installs a 5kW dual-phase energy storage inverter, which can generate 580~600 kWh of electricity per month on average.
    The above is a deceptive article from the media. It claims to be 6KW and only generates 20 kilowatt-hours of electricity every 24 hours! I haven’t explained where to install it. The sun is moving every second.

  3. it is all about unaffordable power prices to destroy industry &drive us back to a third world country . welcome to the greens poverty plan.

  4. “a slew of regulatory flaws in electricity market rules and governance” is this an inference or an outright claim that those doing the reading and writing failed under the compulsory education systems? Aren’t some of these highly educated under tertiary education? It would seem there are many degrees of divergence from reality; as in what works for the benefit of the majority, and how come the minority keep raking in the $$$ benefits of democracy – what’s it’s definition again?

    What next, a claim that tax Acts have holes big enough to let corporations get away with murder?
    It’s a good thing that some were born with the God given right to rule over others, otherwise where would we be with just anyone making up the rules?

  5. You will never get the nominal power on the photovoltaic module.
    That’s just a carrot to lie to the donkey.

  6. If you are not an investor in the power grid, why use someone else’s network? In addition, unstable power will endanger the safety of the power grid. For the power grid, photovoltaic power is garbage power, and garbage disposal fees must be charged.

Leave a comment